Scheduled for May 9, 17:00 CEST - May 10, 17:00 CEST
Scheduled
On Friday, May 9, 2025, preparatory work will take place in preparation for the migration on Saturday.
The migration has been scheduled over the weekend to minimize the impact on daily operations. Key Points:
DNS Change
The DNS change is scheduled for Friday, May 9, 2025, after 17:00. It may take up to 24 hours for the change to fully propagate. As a result, BSNk will no longer be accessible from Friday, May 9, after 17:00.
Migration
The actual migration will take place on Saturday, May 10, 2025. After the transition, you will be connected to BSNkPP in production on the new Picard platform.
Go-Live
Once the migration is successfully completed on Saturday, May 10, we expect you to verify that all functionalities are working as expected.
Posted Mar 14, 2025 - 12:28 CET
This scheduled maintenance affects: eID Hub - eIDs (eHerkenning) and Signicat Identity Broker.